1. Home
  2. Archives
  3. Vol 27 (2020) Issue 1
  4. Articles

Performance Evaluation of Existing Special Bridges in Indonesia Based on SNI 1725:2016 AND SNI 2833:2016 (Case Study of Dr. Ir. Soekarno Bridge)

Abstract

AbtractExisting special bridges such as cable-stayed bridges which are complex in structure need to be evaluated against SNI 1725:2016 and SNI 2833:2016. Dr. Ir. Soekarno Bridge located in Manado, North Sulawesi, was used as case study. Analysis based on the performance of the bridge was conducted using the Nonlinear Static Pushover Analysis (NSPA) with three different load distributions and Nonlinear Time History Analysis (NLTHA). Due to the standard load of the bridge, the deflection was still below the allowable deflection. Girder has an overstress of 12% in the Service Ic combination. The cable also has overstress in Cable 7 between 0.4% and 6.2%. Lower segment pylon capacity was exceeded by earthquake load combination of 28%. Bridge performance shows that the bridge structure was at fully operational performance level and the element performance was at immediate occupancy level, each method shows different result in base shear and displacement. The result shows that re-evaluation for existing special bridges is required. The bridge performance has different base shear and displacement for each method. Nonlinear Time History Analysis is the better option for special bridge, Nonlinear Static Pushover Analysis method requires a further study to determine the ideal load distribution for special bridge because the load distribution is crucial to determine the result of pushover analysis. AbstrakJembatan khusus eksisting seperti jembatan cable stayed yang sangat kompleks perlu dievaluasi kinerjanya terhadap SNI 1725:2016 dan SNI 2833:2016. Studi kasus pada penelitian ini adalah Jembatan DR. Ir. Soekarno di Kota Manado, Sulawesi Utara. Dilakukan pula analisis berdasarkan kinerja dengan Nonlinear Static Pushover Analysis dengan tiga pola beban dan Nonlinear Time History Analysis. Akibat beban standar jembatan, lendutan yang terjadi masih dibawah lendutan ijin. Girder mengalami kelebihan tegangan sebesar 12% pada kombinasi beban Layan Ic. Kabel juga terjadi kelebihan tegangan pada Kabel 7 antara 0,4% sampai 6,2%. Kapasitas pylon segmen bawah terlampaui oleh kombinasi beban gempa sebesar 28%. Analisis kinerja struktur jembatan dengan dua metode didapatkan bahwa tingkat kinerja struktur adalah fully operational dan kinerja elemen adalah immediate occupancy, akan tetapi nilai base shear dan perpindahan berbeda untuk masing-masing metode. Hasil analisis menunjukkan bahwa jembatan khusus eksisting perlu di evaluasi ulang terhadap peraturan terbaru. Kinerja jembatan dengan dua analisis nonlinier yang dilakukan menunjukkan hasil yang berbeda, Nonlinear Time History Analysis tetap menjadi metode yang lebih baik untuk jembatan khusus sedangkan metode Nonlinier Static Pushover Analysis perlu penelitian lanjutan untuk menentukan distribusi beban pushover yang cocok digunakan untuk jembatan cable stayed, mengingat pola distribusi beban sangat menentukan hasil dari analisis pushover.

Keywords

4. Analysis of Bridge Structure Performance Due to Standard Loads

The bridge structure performance against the standard load is assessed based on the deflection of the bridge floor, the stress on the girder, the stress on the cable, and the pylon capacity. Differences in bridge performance parameters during design and evaluation time are shown in Table 3.

Table 2. Performance level of the bridge structure

LevelDescriptionSteel
Strain
Concrete
Strain
% DriftDisplacement
Ductility
IFully
operational
<0.005<0.0032<1.0<1.0
IIOperational0.0050.00321.01.0
ШLife safety0.0190.013.02.0
IVNear collapse0.0480.0275.06.0
vCollapse0.0630.0368.78.0

According to Table 3, the evaluation of allowable deflection is L/250 for service loads and L/800 for vehicle loads. From the analysis results, the deflection value for service load and vehicle load was still below the allowable deflection as shown in Table 4.

The allowable stress requirement on the bridge girders uses the SNI 2847: 2013 Structural concrete requirements for buildings. The allowable compressive stress is 0.45fc = 18.67 MPa and the allowable tensile stress is 0.62fc = 4.011 MPa. The results of the stress analysis on the girder can be seen in Table 5. The girder stress due to service load was still below the allowable stress except for the Ic Load where there was an overstress of 112% (4.49 MPa).

The maximum allowable cable stress was taken from Cable-stayed Bridge Technical Planning Guidelines No. 08 of 2015. The allowable stress is 0.45fpu = 0.45x1860 = 837 MPa for the service load and 0.6fpu = 0.6x1860 = 1116 MPa for the ultimate load. From the results of the analysis, it was found that most of the stress that occurred was still below the allowable voltage, except for several combinations that exceeded the allowable stress on cable 7 (see Table 6).

Pylon was analyzed based on its capacity from the interaction diagram. The results of the analysis show that the pylon structure is still capable of carrying ultimate loads and service loads except for the lower pylon. In the lower pylon, the force caused by the combination due to earthquake load (Extreme I) cannot be borne by the pylon. To verify this, an additional analysis was conducted using the SpColumn program (see Table 7).

From the SpColumn results, there was a value of \(\Phi\)Mn/ Mu smaller than one, which was the load combination of Extreme Ix and Extreme Iy, which was a

Table 3. Bridge performance parameters

ParametersDesign CıriteriaEvaluation Criteria
DeflectionRSNI T-12-2004 Planning of ConcreteL/250 & L/80008_SE_M_2015 Cable-stayed Bridge Technical Planning GuidelinesL/400 & L/800
Girder StressStructures for Bridges Planning of Concrete Structures for BridgesSNI 2847:2013
Compressive0,45fc'Compressive0,45fc'
Tensile0,5√fc'Tensile0,62√fc'
Pylon CapacitySNI 2847:2002Reduction 0,7 - 0,8SNI 2847:2013Reduction 0,7 - 0,9
Cable ForceRSNI T-12-2004 Planning of Concrete Structures for BridgesCable-stayed Bridge Technical
Planning Guidelines (2015)
Service Load0,45fpuService Load0,45fpu
Ultimate Load0,6fpu

Tabel 4. Deflection due to standard load SNI 1725:2016

LoadingDeflection FRequirementsDeflection from Csi Bridge
CombinationRequirementsValue (mm)Max (mm)Min (mm)Desc.
Service 1aL/250480,002,33-32,97OK
Service 1bL/250480,00190,05-151,64OK
Service 1cL/250480,00184,19-150,14OK
Service 2L/250480,00-0,67-66,41OK
Service 3L/250480,007,58-15,10OK
Service 4L/250480,0086,63-5,65OK
Vehicle LoadL/800150,00-1,94-29,46OK

combination of earthquake load. The lower pylon structure can be concluded as not being able to bear the load of an earthquake.

5. Performance Based Analysis

5.1 Nonlinear static pushover analysis

The pushover analysis is a static procedure in which a lateral load pattern is applied to a structure and the load is gradually increased until the displacement of the structure reaches its limit state. Prior to pushover the structure will be loaded by the bridge's fixed load in the form of dead load and additional dead load, plus a traffic load of 50%. Figure 5 shows the capacity curves with three load distribution patterns used, which are the uniform distribution load, static equivalent distribution, and modal analysis distribution.

Using the Csi Bridge program, an analysis with the Capacity Spectrum Method was used to determine the bridge performance. The performance point was obtained

Tabel 5. Stress on girder beam due to service SNI 1725:2016

LoadingGirderTop Fiber StressBottom Fiber Stress
CombinationPositionMaxMinMaxMin
Service Ia 2016Left Girder-2,159-11,303-2,436-13,988
Service la 2016Right Girder-2,160-10,938-2,796-13,759
Service Ib 2016Left Girder-1,080-11,9993,573-16,712
Right Girder-1,198-11,6283,414-16,937
Service Ic 2016Left Girder-1,173-11,9734,491-16,998
Service ic 2016Right Girder-1,131-11,6264,156-17,107
Service II 2016Left Girder-1,530-11,013-2,532-15,688
Service II 2010Right Girder-1,449-11,019-2,608-15,796
Service III 2016Left Girder-2,565-11,122-2,007-12,930
Service III 2016Right Girder-2,482-11,116-2,203-13,027
Service IV 2016Left Girder-3,462-11,0941,789-13,585
Scivice IV 2010Right Girder-3,439-10,9111,454-13,672

by finding a meeting point between the capacity curve and the demand curve in the form of ADRS. The results of the analysis in determining the performance point of the bridge structure can be seen in Figure 6.

Bridge element performance was also required, which was obtained from the moment-curvature value that occurred on the bridge element. In this study, the element performance evaluation was focused on the structure of the lower segment pylon because it was the most critical element. Figure 7 shows the performance point achieved by the lower segment pylon.

From the two results of performance analysis, it can be concluded that from the pushover analysis with the three load patterns used, the structure and elements of the bridge were still safe. The performance level of the

Table 6 Overstress on cable no 7

Cable No.Load CombinationLNSSNSLSSSSS
Cable Stress%fpuCable Stress%fpuCable Stress%fpuCable Stress%fpu
Strength la1162,029104,1%1145,796102,7%1184,858106,2%1150,530103,1%
Strength lb1003,51189,9%987,18988,5%1156,338103,6%1122,031100,5%
S7 (2016Strength Ic1137,074101,9%1121,003100,4%1030,42192,3%996,08689,3%
Load)Strength II1111,61299,6%1095,40998,2%1134,584101,7%1100,25398,6%
Extreme Ixa Max1105,22799,0%1088,30597,5%1128,816101,1%1094,97098,1%
Service II841,298100,5%828,87899,0%859,191102,7%832,78599,5%

Table 7. SpColumn analysis results for lower segment pylon

No.LoadingPuMuxMuyФМпхΦMnyΦMn/
INO.CombinationkNkNmkNmkNmkNmMu
1Strength Ia85.529,3035,8011.261,70867,38272.853,4724,23
4Strength la82.568,50- 7,0010.470,00- 180,37269.790,5325,77
5Strength Ia81.008,30- 228,9093.543,50- 655,98268.067,972,87
6Strength Ia72.205,60- 157,107.699,00- 5.259,54257.752,0033,48
7Strength la74.824,70- 45,6037.034,40- 321,77261.285,037,06
8Extreme Ix Max67.751,30345.232,4194.920,70220.467,3860.616,910,64
9Extreme Ix Min82.650,00-345.363,91- 73.350,10-238.549,27- 50.664,280,69
10Extreme Iy Max50.937,50125.230,80286.493,6991.097,49208.406,080,73
11Extreme Iy Min99.464,00-125.362,00-264.923,00-113.853,10-240.601,730,91
12Service Ia62.700,00173,8028.471,201.507,86247.012,948,68
13Service Ib59.716,2026.112,8027.791,20157.979,41168.133,566,05
14Service Ic59.780,30- 25.699,6027.620,60-157.237,45168.990,646,12
15Service II62.882,5073,406.008,503.018,04247.057,5541,12
16Service III59.229,2035,704.871,701.778,98242.764,7849,83
17Service IV57.661,10- 101,8046.357,70- 529,16240.965,975,20
3 4

Figure 5. Capacity curves

6 7

Figure 6. Pushover curves

bridge was at the fully operational level and the performance level of the bridge element was at the immediate occupancy level. Analysis of the girder stress and cable stress shows that overstress occurred on the bottom side of the bridge girder of 148% to 400% of the allowable stress, while the cable stress was far from the cable yield stress.

5.2 Nonlinear time history analysis

The Nonlinear Time History Analysis used the ground motion taken from the PEER Ground Motion Database. The stages in this analysis were the selection of ground motion and spectral matching, structural analysis using the Csi Bridge program and determination of bridge performance level. The choice

1

Figure 7. Lower segment pylon element performance due to NSPA

3

Figure 8. Lower segment pylon element performance due to NLTHA

of the earthquake was based on parameters from the Ground Motion Evaluation Procedure for Performance-Based Design, ie the magnitude of the earthquake is in the range of \(\pm\) 0.25 target magnitude, the distance to the source of the earthquake fault must be appropriate, and the ground condition must also be appropriate. These parameters were searched by using the earthquake data that occurred around Manado. The data was obtained from BMKG Online. From the data, it is known that the maximum earthquake magnitude that occurred was 6.1 and the maximum closest distance to the earthquake fault was 9.15 km. The ground condition data was obtained from the picture of the plan where the ground condition was in the form of medium ground with shear wave velocity between 175 m/s to 350 m/s. Therefore, four ground motions were selected according to Table 8.

On those ground motions, spectral matching was then carried out in the range of 0.2T to 1.5T. The ground motion input was carried out in the x, y and z directions. The parameters used in the Csi Bridge program were as follows:

Damping used was the proportional damping of 5% with a coefficient calculated by Csi Bridge.

Table 8. Selected ground motions

Record
Sequence
Number
Earthquake NameYearMagnitudeDistance to
Fault
V30 (m/s)
232Mammoth Lakes-0119806,064,67346,82
461Morgan Hill19846,193,48281,61
4146Parkfield-02 CA20046,009,14341,70
8118Christchurch New Zealand20116,209,06263,20

Time integration used was the Newark method with a value of Gamma = 0.5; Beta = 0.25.

The results of the analysis can be seen in Table 9, then the envelope value was selected to determine the structure performance level. The direction of displacement and base shear were reviewed only in the x (longitudinal) and y (transversal) directions. The performance of the elements represented by the lower segment pylon elements is shown through the momentcurvature included in Figure 8.

It can be concluded that from Nonlinear Time History Analysis with four ground motions that were used, both the structure and elements of the bridge were still in a safe condition. The performance level of the bridge was at the fully operational level and the performance level of the bridge element was at the immediate occupancy level. Analysis of the girder stress and cable stress shows that overstress occurred on the bottom side of the bridge girder of 110% to 240% of the allowable stress, while the cable stress was far from the yield stress.

5.3 Discussion on the results of NSPA and NLTHA

Based on the results of the nonlinear static pushover analysis and nonlinear time history analysis, the bridge performance was at the fully operational level with the immediate occupancy element performance level. Despite having the same level of performance, the value of the base shear and displacement that occurred

Table 9. Nonlinear time history analysis results

Record
Sequence
Earthquake NameMax/MinBase Shear (kN)Displacement (m)
NumberX DirectionY DirectionX DirectionY Direction
232Mammoth Lakes-01Max62.235,990.712,20,1640,215
Min- 53.771,3- 57.566,5-0,140-0,226
461Morgan HillMax49.531,084.214,80,1530,195
Min- 55.238,7- 65.649,9-0,174-0,230
4146Parkfield-02_CAMax38.617,388.021,30,1640,203
Min- 58.741,1- 71.304,0-0,185-0,208
8118Christchurch_New ZealandMax54.830,876.504,60,1830,229
Min- 61.081,1- 67.805,6-0,130-0,231

were different. These differences can be seen in Table 10.

From the results in Table 10, it can be concluded that the pattern of load distribution used would determine or influence the results of the analysis. Of the 3 load patterns used in nonlinear static pushover analysis, the value of the base shear approaching the results of nonlinear time history analysis was the modal analysis distribution, while the displacement value obtained was still quite large.

6. Conclusions and Recommendations

  • With a standard load, there were several bridge elements that exceeded the allowable stress. The girder has an overstress of 12% and cable 7 has an overstress of 6.2%. The capacity of the lower segment pylon has also been exceeded by 128%.
  • The results of the NSPA and NLTHA analysis show that the bridge category was still in the safe category, which was fully operational with the immediate occupancy element performance. Cable stress when the performance point was reached was still far from the yield stress, while the bridge girder has overstressed at the bottom by 110% to 400% of the allowable stress.
  • From point a and point b above, it is recommended that any special bridges built before SNI 1725: 2016 and SNI 2833: 2016 apply to be re-analyzed using these regulations. This is to anticipate the possibility of the bridges needing additional strengthening as the impact of the increased loads.
  • On special bridges, especially cable-stayed bridges, the results of nonlinear time history analysis are still better than nonlinear static pushover analysis. Further study is required to determine the ideal pushover load distribution for cable-stayed bridges, considering that the load distribution pattern is crucial in determining the result of pushover analysis.

7. References

Aviram, Ady., Mackie, Kevin R., Stojadinović, Božidar., 2008, Guidelines for Nonlinear

Table 10. Base shear and displacement values

Lateral Load PatternsDirectionBase Shear
(kN)
Displacement (m)Desc.
DesainLongitudinal36537,57-
DesainTransversal91022,90-
NSPA UniformLongitudinal25956,780,357
DistributionTransversal48686,140,295
NSPA StaticLongitudinal20935,690,437
Equivalent DistributionTransversal28656,650,319
NSPA Modal AnalysisLongitudinal42212,050,283
DistributionTransversal52405,670,148
62235,910,185Max
NT TILLLongitudinal38617,340,130Min
NLTHA90712,240,301Max
Transversal57566,480,203Min

Analysis of Bridge Structures in California, Pacific Earthquake Engineering Research Center, California.

Badan Standarisasi Nasional, 2005, RSNI T-02-2005 Standar Pembebanan Untuk Jembatan, Indonesia.

Badan Standarisasi Nasional, 2013, SNI 2847-2013 Persyaratan Beton Struktural Untuk Bangunan Gedung, Indonesia.

Badan Standarisasi Nasional, 2016, SNI 1725-2016 Pembebanan Untuk Jembatan, Indonesia.

Badan Standarisasi Nasional, 2016, SNI 2833-2016 Perencanaan Jembatan Terhadap Beban Gempa, Indonesia.

Departemen Pemukiman dan Prasarana Wilayah, 2004, Pd T-04-2004-B Pedoman Perencanaan Beban Gempa Untuk Jembatan, Indonesia.

Fajfar, Peter., 1999, Capacity Spectrum Method Based On Inelastic Demand Spectra, Earthquake Engineering And Structural Dynamics, 28, 979-993.

Federal Emergency Management Agency, 2000, Prestandards and commentary for Seismic rehabilitation of Building (FEMA-356), Washington.

6LQDWUDGNN

  • .DONDQ (URO 'DQ &KRSUD $QLO . 3UDFWLFDO *XLGHOLQHV WR 6HOHFW DQG 6FDOH (DUWKTXDNH 5HFRUGVIRU1RQOLQHDU5HVSRQVH+LVWRU\$QDO\VLV RI6WUXFWXUHV8QLWHG6WDWHV*HRORJLFDO6XUYH\
  • .HPHQWHULDQ 3HNHUMDDQ 8PXP GDQ 3HUXPDKDQ 5DN\DW 6( 1R 6(0 7HQWDQJ 3HUHQFDQDDQ 7HNQLV -HPEDWDQ %HUXML .DEHO ,QGRQHVLD
  • .HPHQWHULDQ 3HNHUMDDQ 8PXP /DSRUDQ )LQDO ,QGHSHQGHQW3URRI&KHFN-HPEDWDQ&DEOH6WD\HG 'U ,U 6RHNDUQR 37 0DUDWDPD &LSWD 0DQGLUL %DQGXQJ
  • 1DWLRQDO&RRSHUDWLYH+LJKZD\5HVHDUFK3URJUDP 3HUIRUPDQFH %DVHG 6HLVPLF %ULGJH 'HVLJQ 7UDQVSRUWDWLRQ5HVHDUFK%RDUG:DVKLQJWRQ
  • 6LQDWUD)UDQV(YDOXDVL.LQHUMD-HPEDWDQ.KXVXV (NVLVWLQJ GL ,QGRQHVLD %HUGDVDUNDQ 61, GDQ 61, 6WXGL .DVXV -HPEDWDQ '5 ,U 6RHNDUQR ,QVWLWXW 7HNQRORJL %DQGXQJ%DQGXQJ
  • 6WHZDUW-RQDWKDQ3&KLRX6K\K--HQJ%UD\-RQDWKDQ ' GNN *URXQG 0RWLRQ (YDOXDWLRQ 3URFHGXUHV IRU 3HUIRUPDQFH-%DVHG 'HVLJQ 3DFLILF(DUWKTXDNH(QJLQHHULQJ5HVHDUFK&HQWHU &DOLIRUQLD

Performance Evaluation of Existing Special...

Research Intelligence

Data from OpenAlex ↗

Metrics

2
Citations
0.15
FWCIfield-weighted
47th
Percentilevs same year + field
Article
Work type
Open Access

Citation Trend

Citation Timeline

YearCitations
20241
20231

Semantic Profile AI-classified research signals

Institution Network

References

  1. Aviram, Ady., Mackie, Kevin R., StojadinoviA, BoA3/4idar., 2008, Guidelines for Nonlinear Analysis of Bridge Structures in California, Pacific Earthquake Engineering Research Center, California.
  2. Badan Standarisasi Nasional, 2005, RSNI T-02-2005 Standar Pembebanan Untuk Jembatan, Indonesia.
  3. Badan Standarisasi Nasional, 2013, SNI 2847-2013 Persyaratan Beton Struktural Untuk Bangunan Gedung, Indonesia.
  4. Badan Standarisasi Nasional, 2016, SNI 1725-2016 Pembebanan Untuk Jembatan, Indonesia.
  5. Badan Standarisasi Nasional, 2016, SNI 2833-2016 Perencanaan Jembatan Terhadap Beban Gempa, Indonesia.
  6. Departemen Pemukiman dan Prasarana Wilayah, 2004, Pd T-04-2004-B Pedoman Perencanaan Beban Gempa Untuk Jembatan, Indonesia.
  7. Fajfar, Peter., 1999, Capacity Spectrum Method Based On Inelastic
  8. Demand Spectra, Earthquake Engineering And Structural Dynamics, 28, 979-993.
  9. Federal Emergency Management Agency, 2000, Prestandards and commentary for Seismic rehabilitation of Building (FEMA-356), Washington.
  10. Kalkan, Erol. Dan Chopra, Anil K., 2010, Practical Guidelines to Select and Scale Earthquake Records for Nonlinear Response History Analysis of Structures, United States Geological Survey.
  11. Kementerian Pekerjaan Umum dan Perumahan Rakyat, 2015, SE No. 08/SE/M/2015 Tentang Perencanaan Teknis Jembatan Beruji Kabel, Indonesia.
  12. Kementerian Pekerjaan Umum, 2012, Laporan Final Independent Proof Check Jembatan Cable Stayed Dr. Ir. Soekarno, PT. Maratama Cipta Mandiri, Bandung.
  13. National Cooperative Highway Research Program, 2013, Performance Based Seismic Bridge Design, Transportation Research Board, Washington.
  14. Sinatra, Frans, 2018, Evaluasi Kinerja Jembatan Khusus Eksisting di Indonesia Berdasarkan SNI 1725:2016 dan SNI 2833:2016 Studi Kasus Jembatan DR. Ir. Soekarno, Institut Teknologi Bandung, Bandung.
  15. Stewart, Jonathan P., Chiou, Shyh-Jeng., Bray, Jonathan D., dkk., 2001, Ground Motion Evaluation Procedures for Performance-Based Design, Pacific Earthquake Engineering Research Center, California.